Road Improvement Plan
Willis Road, Platt Road, Bemis Road, US-23
Tentative Work Schedule
Subject to change
NOTE: While some of the roads will be open while they are being worked on there will be relatively short term, temporary lane closures.
Stage 1 Sept. 13, 2007 through November 15, 2007
Platt Road north of Willis Road to Bemis Road – closed – existing roadway replaced
Willis Road – open – new roadway construction north of existing roadway
Stage 2 March 3, 2008 through April 24, 2008
Platt Road south of Willis – closed – new roadway construction
Willis Road – open – existing roadway replaced, traffic diverted onto new roadway
US23 Southbound Entrance Ramp – open – existing ramp replaced
Stage 3A April 25, 2008 through May 13, 2008
Willis Road west of Platt to Emerson – closed – construct new roadway
Stage 3B May 14, 2008 through June 2, 2008
Willis Road east of US23 Southbound Exit Ramp – closed – widen pavement for left turn lane
US23 Southbound Exit Ramp – open - widen pavement
Stage 4 June 3, 2008 through June 11, 2008
Bemis Road at Platt Road – closed – widen pavement for turn lane
Platt Road at Bemis Road – open (intermittent lane closures) – widen pavement for turn lane
Stage 5 June 12, 2008 through June 26, 2008
Platt Road north of Bemis – closed – widen pavement for turn lane
Stage 6 June 27, 2008 through July 2, 2008
Willis Road – open (intermittent lane closures) – apply pavement top course
Platt Road – open (intermittent lane closures) – apply pavement top course
Bemis Road – open (intermittent lane closures) – apply pavement top course
Stage 7 July 3, 2008 through July 16, 2008
US23 Northbound exit ramp – open – widen pavement for turn lane
Stage 8 July 17, 2008 through August 1, 2008
US23 Northbound entrance ramp – open – widen pavement
Willis Road east of US23 – open – widen pavement for turn lane